I&C&E Hardened Containment Vent

As part of a fukushima modification, BHI worked with Energy NW to install an electrical portion of the Hardened Containment Vent (HCV) system within the plant and control room while the unit remained online. The project involved running 1,200ft of conduit and installing 2,500ft of cable, as well as installing HCV batteries, battery charger, distribution panel, associated cables, conduit, termination boxes, splice and pull boxes. The project was conducted as a managed task within BHI’s Target Price model.  With strong performance BHI has conducted ongoing work with the customer.